CALSTATE weekly call
Wednesday, June 01, 2016
1. Test load status highlights- as of 6/1/16
o 14 institutions have been released to the project team for checks
o 12 institutions have been given the go-ahead for copy to production
o 2 institutions have open questions that need to be resolved before moving to the next step (Pomona, Maritime)
o Alma configuration forms have been finalized for all except for Moss Landing and Humboldt (we are checking those now)
o Status: ok
2. Upcoming activities:
· Test load delivery - Jun 9
· Copy of San Marcos and Sacramento institutions (post Jun 9)
· Next Alma functional call (Fulfillment) - Jun 16
· Analytics trainings - Jun 21 and Jun 27
· First look at Primo - Jul 15
3. July Certification deadline:
o Action: Audrey will sign July people up by deadline. Please get your names into the CALSTATE sign-up sheet by Jun 24. Brandon will send Audrey finalized list of names by EOB Jun 24.
4. Go-live dates:
o Action: Audrey to send Brandon the confirmed migration dates today
o Action: Brandon will socialize information to COLD and others by next week